Capacity Planner & Resource Management

Compare estimated work with each person's working hours in Calendar and Workloads to maintain productivity while avoiding burnout.

Written by Team

Capacity is calculated using your team’s working hours and availability, then compared against the effort assigned to tasks through Estimates or Story Points.

Together, Calendar and Workloads give you a consistent view of team capacity so you can distribute work more effectively and avoid overloading teammates.

Benefits of Capacity Planning

Capacity planning helps teams make better decisions about when and where work should be assigned. You can use it to:

  • Estimate task effort: Define how much time or effort a task is expected to require.

  • Understand team availability: See how much working capacity each teammate has based on their schedule and time off.

  • Balance workloads: Compare assigned effort against available capacity before workloads become excessive.

  • Plan project delivery: Understand how much effort is required across tasks, Lists, and milestones.

  • Schedule work more effectively: Use Calendar to see when teammates have availability and adjust assignments directly.

Estimates & Story Points

Nifty supports two ways to estimate the effort required for a task:

  • Estimates measure effort in time, such as 30m, 2h, or 8h.

  • Story Points measure effort using points, with each point converted to a configurable number of working hours.

Both ultimately allow Nifty to compare the effort assigned to a teammate against their available working capacity. You can choose Hours, Story Points, or None as the default estimation method for your workspace and override that setting for individual projects.

Setting up capacity planning

Open Control Center → Workspace → Planning.

  1. Under Estimation, choose Story points, Hours or None.

  2. Pick your workspace time zone.

  3. Set the working hours for each day. Drag an edge to move an hour, or click a day to type exact times. Use a day's ⋯ menu to mark it as a day off.

  4. Click Give someone their own hours for anyone who works a different schedule. Set their time zone, days and hours.

  5. Turn on Disable weekends to hide weekends in the calendar and timeline.

The weekly total updates as you change the hours. For example, 8 hours a day Monday to Friday is 40 hours of capacity a week, before time off.

Changing the unit for one project

Open the project's Control Center, go to General, and change Estimation unit. Choose Inherit from workspace to use the workspace default.

Adding estimates to tasks

  1. Open a task and click + next to its dates.

  2. Click Estimate.

Enter the estimate. Estimates and story points work on subtasks too.

Seeing capacity in Calendar

Calendar shows each person's day, their work and the time they have left.

  1. In Day view, group by Assignee to give each person their own column.

  2. Each column shows hours committed against hours available. Days over capacity are highlighted.

If capacity isn't showing:

  1. Click the eye icon.

  2. Check Capacity.

From Calendar you can drag tasks between people to reassign them, drag unscheduled tasks onto a day, update estimates, and create tasks, events or time away from an empty slot. Group by Project to compare project schedules instead.

Seeing capacity in Workloads

Go to Reporting → Workloads for a week at a glance.

  1. Pick the period.

  2. Click Filter to narrow by project or tags.

Tracking story points on the Roadmap

In projects that use story points, each milestone shows two kinds of progress: the share of tasks completed, and the share of story points completed.

Capacity Planning FAQs

> How do Story Points translate into capacity?

Story Points are converted into working time based on the value configured under Control Center → Planning → A day is worth. This allows Story Point-based workloads to use the same underlying working-hours model as hour-based Estimates.

> Will Nifty prevent me from assigning someone over capacity?

No. Nifty will show when assigned effort exceeds a teammate’s available capacity, but it will not prevent additional work from being assigned.

> How does time off affect capacity?

Time off reduces a teammate’s available capacity for the affected day or period and is reflected in Calendar and Workloads.

> Can teammates have different working hours?

Yes. Workspace working hours act as the default, while individual teammates can have their own working schedule and time zone.

> Can I exclude weekends from capacity planning?

Yes. Workspace Owners can choose whether weekends count as working days from Control Center → Planning.

> What happens when a task has multiple assignees?

The task’s estimated effort is attributed in full to each assignee rather than being divided between them.

> Can different projects use different estimation methods?

Yes. Your workspace has a default estimation method, but individual projects can override it with their own setting.

> Can I use Estimates on subtasks?

Yes. Estimates and Story Points can be added to subtasks just like top-level tasks.